2015-05-04 - 16728 - Spec - SNC Single Work Order #SNCProject #ABAPSNC

SPECIFICATIONS

2015-05-04 - 16728 - Spec - SNC Single Work Order Process.

Purpose


Create a Single Work Order in SNC per Purchase Order to minimize the user confirmation.

Admin Info


Purpose
SNC Single Work Order Process
Requested By
Jeffery Mau
Spec Created By
Adithya, Venkat
Spec Created Date
05/07/2015
Spec QA by
Adithya,
Objects

Document Status
Closed - This option is not used in the Simplified WO Process

Estimates


Sl.No
Activity
Estimation in Hours
1
Research
08
2
Documentation

3
Development/ Config
112
4
Unit test in DEV
40
5
Unit test in QUA

6
Other activity


TOTAL
160
References

Prior Tickets

[Provide links of prior associated Spec / Break Fix BOSS document(s)]
Three Options were given for this requirement which are specified in the document attached below:
SCM - 2015-04-14 - 16728 - Spec - SNC Approach on Single Work Order Create for a PO

Documents
[Attach any document(s) received for the requirement(s)]

Spec Changes


[List the changes made to program after the approval of the original requirement along with the Date on which the change request was received and the name of the initiator]

Sl.
Change Details
Requested By
Requested On
Notes if any





Functional Requirement


Purpose/WHY:

[Explain the purpose of the project and the reason why this requirement has come]

Currently Work Orders (WOs) are created at Purchase Order item level. This creates user and system issues that need to be addressed:
  1. High number of user confirmations required- If there are many lines in the PO, multiple WOs are created one per a PO Line.For example, : If a PO has 500 lines system creates 500 work orders then the user has to click 500 items for each phase of a WO.
  2. Confirmation Idocs fail and have to be manually reprocessed.

In Scope:

[List the activities to be included in scope]
All POs sent to SNC only.

Out of Scope:

[Out of scope activities]

Solution Summary


[Discuss this section with Requester and get approval prior to beginning work]
New Era would like to create a single work order (with 4 reporting phases) for the PO. Any statuses confirmed on this item would be updated on all other items of the ECC PO via a program. Unfortunately a single WO cannot be created at the header level. Therefore such a single WO would need to be created line level. There are the three options for line level WOs:

Out of the three options provided NE has chosen option 1 which is:

Users will confirm status on only one Active Item of the PO.
- The current WO list program will be replaced by a program to create only one Work list for the first active item.
- Statuses reported on this WO will be presumed to be for the ENTIRE PO.

- If the first active item is subsequently deleted in ECC, another Work list will be generated for reporting *** To be discussed. May not be required if no PO changes are allowed after Publish.

Test Plan

[List test scenarios/cases to be executed here]
Test ID
Test Scenario
Expected Results
SNC001
end to end cycle for order type NB without any line deletions.
Outputs and document data match current multi WL process
SNC002
end to end cycle for order type NB without any line deletions for large POs
Outputs and document data match current multi WL process
SNC003
end to end cycle for order type Z3NB without any line deletions.
Outputs and document data match current multi WL process
SNC004
end to end cycle for order type Z3NB without any line deletions for large POs.
Outputs and document data match current multi WL process
SNC005
Mass Update Program - Validate it works for all non deleted lines only.
Outputs and document data match current multi WL process
SNC006
Work list creation program - Validate it only creates WL for first active item.
Outputs and document data match current multi WL process
SNC007
end to end cycle for order type NB-TAB without any line deletions.
Outputs and document data match current multi WL process
SNC008
end to end cycle for order type NB-TAB without any line deletions for large POs.
Outputs and document data match current multi WL process
End to end cycle for NB PO:
Create a PO
Move to SNC
Print ECC PO
PO Download ECC
Publish PO
Create INB delivery
Create WO
Publish WO
Create WO WL
Update confirmations till ZN
Copy Status for all lines of PO
Create ASN Per SO (Draft)
Update ZP
Update the Data in ASN and Save draft
Publish ASN (Final)
MIGO the PO

End to end cycle for Z3NB PO:
Create a PO
Move to SNC
Publish PO
Create WO
Publish WO
Create WO WL
Update confirmations till ZN
Copy Status for all lines of PO
Create INB delivery
Pack the INB delivery
Print UCC labels
Update ZP
Create ASN Per SO (Draft)
Update the Data in ASN and Save draft
ZASN Forward (Booking & Shipping)
Publish ASN (Final)
Create PGR for INB Delivery
ASN From PGR

Solution Details


[Provide complete technical details for configuration or programming here]

1. The Program to create Work List for the WO of first active line of a PO

Program: ZNEC_WO_WL_CREATE_SINGLE this will be replace the existing program: ZNEC_WO_WL_CREATE

Input Options:
16728_1.JPG

2. The Program to copy the confirmations to the rest of PO lines.

Program: ZPO_CONFIRMATION (this is a new program)
Input options:
a. Date range input:
The confirmations updated in the range of date on active line of POs are considered and copied to the rest of lines.
16728_2.JPG
b. No. of days input:
The confirmations updated in past X days on active line of POs are considered and copied to the rest of lines.
16728_3.JPG

Issues


[List Issues / Bugs identified in configuration or development]